It is anticipated the rebuild of the fire-damaged sawmill at Tolko Industries Ltd. Lakeview Division in Williams Lake will be completed in time to resume full operations in February 2019.

Rebuild of fire-damaged Lakeview mill aiming for full-production by Feb. 2019

The company said it hopes to resume full production by February 2019.

Nine months after a fire destroyed Tolko’s Lakeview Division sawmill in Williams Lake the company said it hopes to resume full production by February 2019.

Randy Chadney, Tolko Industries general manager BC Lumber, told the Tribune the demolition was completed in April and the rebuild is underway, noting the source of the fire could not be determined by the fire inspector, but it was confirmed it was not caused by combustible dust.

“We are reconstructing the sawmill and expect to start testing some of the equipment in November,” Chadney said.

Compared to the previous three-line sawmill at Lakeview, the new one will be a two-line sawmill with a canter line and a head rig.

READ MORE: Tolko resumes rebuilding fire-damaged sawmill in Williams Lake

“We curtailed one of those other lines in 2015, so it wasn’t operating anyways,” Chadney said. “The footprint is similar, it’s just going to be a little more streamlined. That mill was built back in the 50s and it had a lot of additions to it which didn’t make it very efficient.”

Chadney said the rebuild has faced some delays.

“Our initial assessment didn’t seem like it was going to be long to get it back up and running, but with the cold weather this winter and water damage from fighting the fire, when we got into the mill and looked at the equipment, the damage was more severe than we thought it was.”

The sawmill building itself was an old stick-frame building that did not meet code and it was also severely damaged in the fire.

READ MORE: Tolko confirms active fire at Lakeview mill

As a result, Tolko went the route securing a firm to design and build a pre-engineered building.

“We are fortunate that we moved very quickly when we had approval from Tolko to rebuild the mill and were able to get in the queue to purchase equipment. The forest industry is very busy right now and there can be a two-year lead time to order equipment.”

Sometime in August, residents may notice 47 truckloads of materials arriving for the new building, he added.

In the meantime, trades employees are rebuilding equipment salvaged from the fire as well as some equipment that was repurposed from the sawmill in Merritt that shut down in 2016.

The electrical group is doing some prep work for the new mill and other employees are doing site security and spark watches.

“We are still taking logs into our log yards, and all the mechanics are still here,” Chadney said.

Engineered soil sampling was also required for the rebuild to ensure the foundations were going to be up to code.

“That was done by our engineer for the mill and the people constructing the building. They did methane gas testing, which came back negative, so that was good. There was a lot of permitting stuff that had to be done around landfill issues, but we did really well.”

With so much water at the site each spring, a new water drainage plan with better drainage is being developed, specifically around the perimeter of the building.

Town hall meetings are held every few months at the Cariboo Memorial Complex with employees to update them on the progress of the rebuild. The last one was in mid-July.

Presently 117 hourly employees who were at the Lakeview sawmill before the fire are still working for Tolko — 65 at Lakeview, 37 at Soda Creek Division and 15 in Quesnel.

“Our company and the union have worked together really well to accommodate everybody in this pretty poor time,” Chadney said.



news@wltribune.com

Like us on Facebook and follow us on Twitter

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Comments are closed

Just Posted

Horsefly Volunteer Fire Dept. certifies in swiftwater rescue technician

Ten members trained with instructor Jordan Thompson

Station House Gallery eyes reopening with unique shows

When the next art exhibit opens at Williams Lake’s The Station House… Continue reading

Tsilhqot’in Nation demands meeting with feds on declining Fraser River chinook stocks

The Nation wants to partner with DFO to rebuild and recover the stocks

VIDEO: City hosts processions in celebration of Canada’s birthday

Via the Facebook page, there are also several Canada Day-themed crafts taking place

Day camps on this summer at Lake of the Trees Bible Camp

‘We have fought hard to keep camp open’

‘This year is unlike any other’: Trudeau delivers Canada day address

Sophie Gregoire Trudeau and the Prime Minister release video celebrating the national holiday

Facing changes together: Your community, your journalists

Thanks for helping the Williams Lake Tribune continue its mission to provide trusted local news

PHOTOS: Dual rallies take over Legislature lawn on Canada Day

Resist Canada 153 highlighted colonization and genocide, Unify the People called COVID a hoax

Gov. General honours Canadians for bravery, volunteer service

Five categories of winners presented on Canada Day

COVID-19: Should non-medical masks be mandatory in Canada?

New poll shows Canadians are divided on the rules around mandatory masks

‘A little bit scary for everybody’: Air passengers wary as new rules take effect

Masks or face coverings have been mandatory on flights since April 20

VIDEO: Prince William and Kate chat with B.C. hospital staff about COVID-19

Seven-minute video posted to Youtube on Canada Day

River centre says heavy rains could bring flooding to central, northeastern B.C.

Water levels are already unusually high and river banks can be extremely unstable

Most Read