Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Bingo is returning on Thursday, June 17 at Chances Signal Point in Williams Lake. (stock photo Pixabay)
‘Under the B’: bingo is returning to Chances Signal Point in Williams Lake

Adjusted hours of operation will see bingo offered Thursday through Saturday

Salvation Army food bank co-ordinator Tari Davidge, left, and Tamara Robinson, director of family services and community outreach, display a sample kit for the “After the Bell” program that will provide healthy food for children. (Monica Lamb-Yorski photo - Williams Lake Tribune)
Williams Lake Salvation Army running ‘After the Bell’ food program for children in need

The intent is to supply weekly packs of child-friendly nutritious food

Sugar Cane Archaeology archaeologists Tina Herd, left, and Whitney Spearing, title and rights manager for Williams Lake First Nation. (Monica Lamb-Yorski photo - Williams Lake Tribune)
Archaeological assessments underway at Cariboo Memorial Hospital expansion site

Sugar Cane Archaeology testing green space and corner of parking lot

Williams Lake river valley June 2021. (Monica Lamb-Yorski photo - Williams Lake Tribune)
VIDEO: Williams Lake river valley 2020 flood repairs continue

The Tribune toured the area on June 10, 2021

People watch a car burn during a riot following game 7 of the NHL Stanley Cup final in downtown Vancouver, B.C., in this June 15, 2011 photo. THE CANADIAN PRESS/Geoff Howe
10 years ago: Where were you during the 2011 Vancouver Stanley Cup Riots?

Smashed-in storefronts, looting, garbage can fires and overturned cars some of the damage remembered today

Cannabis bought in British Columbia (Ashley Wadhwani/Black Press Media)
Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

(Black Press Media file)
Dirty money: Canadian currency the most germ-filled in the world, survey suggests

Canadian plastic currency was found to contain 209 bacterial cultures

(pixabay file shot)
B.C. ombudsperson labels youth confinement in jail ‘unsafe,’ calls for changes

Review states a maximum of 22 hours for youth, aged 12 from to 17, to be placed in solitary

Eleonore Alamillo-Laberge, 6, reads a book in Ottawa on Monday, June 12, 2017. THE CANADIAN PRESS/Sean Kilpatrick
Parents will need to fight ‘COVID learning slump’ over summer: B.C. literacy experts

Parents who play an active role in educating their children this summer can reverse the slump by nearly 80%, says Janet Mort

Kelowna General Hospital. (File photo)
COVID-19 outbreak at Kelowna General Hospital declared over

Three people tested positive for the virus — two patients and one staff — one of whom died

The border crossing on Highway 11 in Abbotsford heading south (file)
Western premiers call for clarity, timelines on international travel, reopening rules

Trudeau has called Thursday meeting, premiers say they expect to leave that meeting with a plan

The B.C. government’s vaccine booking website is busy processing second-dose appointments, with more than 76 per cent of adults having received a first dose. THE CANADIAN PRESS/Jonathan Hayward
B.C.’s COVID-19 infections, hospitalizations stable for Tuesday

108 new confirmed cases, 139 in hospital, 39 in intensive care

Most Read